From August 2003 Bryden Wood were part of the multidisciplinary design team working on Heathrow Terminal 5.

As part of the Production Design Fit Out team, our work included detail design of stairs, walls, internal roofs, balustrades and handrails, glazing systems, the production of design information for soffit insulation packages and IT ducting packages. Innovative design solutions and a refreshing attitude towards the generation of design package information were required to fulfil project aspirations.

At a cost of £3.7 billion, the overall programme included the terminal buildings, new aircraft stands, the M25 spur road, two rail stations and the Piccadilly Line and Heathrow Express extensions, an air traffic control tower, landscaping, a car park and a hotel. With the addition of a second satellite building and associated facilities, Terminal 5 already exceeded 30m passengers in 2014.