Singapore API Facility Site-Wide Rationalisation

Rationalising a $1bn SGD API facility to reduce cost, carbon and operational demand.

Bryden Wood were initially appointed by a leading global pharmaceutical company to review and optimise the concept stage design for the dry processing building at a new $1bn SGD API (active pharmaceutical ingredient) plant in Singapore. After delivering a radically improved proposal (which was adopted as the client’s preferred design), Bryden Wood’s engagement was extended to include the wet synthesis building and then extended again to consider site-wide rationalisation opportunities.

Project details:

At every step, our rationalised proposals reduced operational costs and resulting CO2 emissions.

Including:

  • 10% annual reduction in MVAC load

  • 55% reduction in boiler demand

Reduction in site footprint and overall construction material quantities and costs resulted in an estimated 20% overall CAPEX reduction without reducing functionality.


Lessons from the study were adopted in the detailed design and delivery of the plant which received an ISPE Facility of the Year award in 2024.